Gemland Residence remains on schedule for project completion, with key finishing
and testing activities underway.
Project on Track
Amenity areas are actively progressing, enhancing the lifestyle experience Gemland will offer.
Parking Floors: 90% complete – railings and painting in done
Corridors & Lobbies: 95% complete – lighting ongoing
Swimming Pool: 60% complete – waterproofing done
Gym Area: 60% complete – wall finishes and floor prep in progress
Common Areas & Amenities
Lift Installation: Completed and operational
Lighting Fixtures: 90% installed (up to 19th floor)
Electrical Cabling: 100% complete
CCTV Installation: 50% complete (up to 10th floor)
Toilet Fittings: 75% complete (20th floor ongoing)
Mechanical, Electrical & Plumbing (MEP)
All apartments are now fully fitted with cabinetry and doors, enhancing interior readiness.
Kitchen Cabinets: 100% complete (with granite tops)
Bedroom Cabinets: 100% complete
Main Doors: 100% complete
Internal Doors: 100% complete
Joinery & Carpentry
All internal floors and walls are complete, with touch-ups ongoing in select areas.
Corridor & Apartment Tiling: 100% complete
Skirting: 100% complete
Gypsum Ceilings: 100% complete
Wood Paneling: 95% complete
Internal Finishing Works
Final exterior finishes are being applied as the building nears handover readiness.
Exterior Painting: 70% complete
Glass Railings: Fully completed
Window Panels: Fully installed
Exterior & Structural Works
Gemland Residence has reached the final finishing phase, with over 90% overall completion. Major
milestones include completion of cabinetry, doors, tiling, and lift installation. Work now focuses on
external finishes, amenity areas, and final system testing.